Steves & Sons · ERP Program · Phase 1
Infor CloudSuite + Shipwell Command Center
Last updated Oct 20, 2026 by Ruth Spina · Executive sponsor Jason Jennings · Program owner Ruth Spina
Days to go-live
224
Production go-live Jun 1, 2027
Next milestone
6d
I-01 Project kickoff · Oct 26, 2026
Infor status
Infor CloudSuite lane
Shipwell status
Shipwell TMS lane
Open actions
22
6 due in 7 days · 7 missing owner or date · 1 completed
Integrated timeline
Infor CloudSuite
LN · Financials · Factory Track · EPM
Shipwell TMS
TMS · JB Hunt 360 · EDI 210
Finance readiness
Conversion and cutover gates
Selected milestone
Production go-live
- Status
- On track
- Baseline
- Jun 1, 2027
- Forecast
- Jun 1, 2027
- Time remaining
- 224 days
- Accountable owner
- Ruth Spina
What this means
Steves begins running the business on Infor CloudSuite in production. Shipwell goes live the same day.
Identified Oct 19, 2026 by Joaquin Cabrera, Infor · Source: Infor pre-kickoff executive alignment deck
No date changes recorded.
Actions driving this milestone
No action items are linked to this milestone yet.
Decisions and risks
4 decisions pending · 4 open risks · 3 without a needed-by date
| Type | What executives need to know | Track | Owner | Needed by |
|---|---|---|---|---|
| Decision D-02 | Confirm the Steves team by domain SMEs, data owners, testers and decision-makers. | Infor CloudSuite | Ruth Spina | Oct 23, 2026 |
| Risk R-01 | Dev and Data team carries the Shipwell integration alongside Infor work Capacity must be planned in the integrated schedule. | Shipwell TMS | Luis Gonzalez (Dev) / Mark Walther (Data) | Nov 20, 2026 |
| Decision D-03 | Historical data scope and change order Years and detail level per source; Infor vs. data lake. | Finance readiness | Jason Jennings | Date needed |
| Decision D-04 | Chart of accounts and bank GL structure Segment structure and one GL per bank account. | Finance readiness | Jason Jennings | Date needed |
| Decision D-05 | Document management Laserfish upgrade vs. Infor IDM / Velocity Suite. | Finance readiness | Jason Jennings | Date needed |
| Risk R-02 | Infor slips pass straight through to Shipwell Shipwell is excused for delays caused by Infor. | Shipwell TMS | Ruth Spina | Ongoing |
| Risk R-03 | SME time overlaps month-end close SME time (~75% Nov–Jun) overlaps month-end close; workshops need month-end blackout dates. | Infor CloudSuite | Ruth Spina | Oct 26, 2026 |
| Risk R-04 | Scope creep from a proposed CAPM sales database Plan is sales 100% in Infor, CAPM production only. | Infor CloudSuite | Ruth Spina | Ongoing |
Action items
| ID | Action | Track | Owner | Start | End | Status | Identified |
|---|---|---|---|---|---|---|---|
| A-02 | Confirm SMEs, data owners, IT resources, testers and decision-makers by domain. | Infor CloudSuite | Ruth Spina | Oct 19 | Oct 23 | In progress | Oct 19 · Joaquin Cabrera, Infor |
| A-03 | Share updated resource-involvement matrix. | Infor CloudSuite | Joaquin Cabrera | Oct 19 | Oct 23 | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-04 | Build detailed integrated project plan. | Infor CloudSuite | Ursula Rowland | Oct 26 | Nov 20 | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-05 | Review TST/TRN/PRD access, role-based security, SSO; request Infor security matrix. | Infor CloudSuite | Ruth Spina | Oct 20 | Nov 6 | In progress | Oct 19 · Jason Jennings |
| A-06 | Confirm sample-data availability. | Infor CloudSuite | Owner needed | Oct 19 | Date needed | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-07 | Distribute training roster and slides. | Infor CloudSuite | Julio Medina | Oct 19 | Oct 22 | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-08 | Submit participants and dates for LN Navigation (1 day) and Foundation (4 days) courses, max 7 each. | Infor CloudSuite | Tiffany Schwartz-Rano | Oct 20 | Oct 30 | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-09 | Confirm training recording permissions. | Infor CloudSuite | Julio Medina | Oct 19 | Date needed | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-10 | Confirm Steves access to Infor project management platform. | Infor CloudSuite | Joaquin Cabrera | Oct 19 | Date needed | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-11 | Establish joint project contact directory. | Infor CloudSuite | Owner needed | Oct 19 | Date needed | Open | Oct 19 · Joaquin Cabrera, Infor |
| A-12 | Schedule Shipwell kickoff and baseline Shipwell milestones against Infor plan. | Shipwell TMS | Ruth Spina | Oct 20 | Nov 20 | Open | Oct 20 · Ruth Spina |
| A-13 | Plan Infor LN to Shipwell integration development, unit testing and technical cutover (Dev team). | Shipwell TMS | Luis Gonzalez | Oct 20 | Nov 20 | Open | Oct 20 · Ruth Spina |
| A-14 | Name TMS super users by facility and function. | Shipwell TMS | Ruth Spina | Oct 20 | Nov 20 | Open | Oct 20 · Ruth Spina |
| A-16 | Reconcile facility count (Shipwell SOW scopes up to 4 facilities, SOW overview cites seven, finance cites eight plants). | Shipwell TMS | Ruth Spina | Oct 20 | Nov 6 | Open | Oct 20 · Ruth Spina |
| A-17 | Own integration field mapping and master data readiness: items, addresses, facilities, product cube (Data team). | Shipwell TMS | Mark Walther | Oct 20 | Nov 20 | Open | Oct 20 · Ruth Spina |
| A-18 | Request Infor change order for historical data conversion. | Infor CloudSuite | Ruth Spina | Oct 20 | Date needed | Open | Oct 19 · Ruth Spina |
| A-19 | Define historical data scope: years and detail level per source (Epicor, Esker, Sage), Infor vs. data lake. | Infor CloudSuite | Mark Walther | Oct 20 | Date needed | Open | Oct 19 · Ruth Spina |
| A-20 | Email SMEs on time commitment (Infor estimate ~75% Nov–Jun, 50% Feb–Mar) before kickoff. | Infor CloudSuite | Jason Jennings | Oct 19 | Oct 23 | Open | Oct 19 · Ruth Spina |
| A-21 | Align Infor Concierge, Education portal and TST access for Ruth, Tiffany and Warren (Joaquin sets up, Jason approves). | Infor CloudSuite | Ruth Spina | Oct 19 | Oct 23 | In progress | Oct 19 · Ruth Spina |
| A-22 | Start internal decision log; record Esker retirement and sales 100% in Infor. | Infor CloudSuite | Tiffany Schwartz-Rano | Oct 19 | Oct 30 | Open | Oct 19 · Ruth Spina |
| A-23 | Set weekly internal team meeting directly after each Infor meeting. | Infor CloudSuite | Ruth Spina | Oct 19 | Oct 26 | Open | Oct 19 · Ruth Spina |
| A-24 | Provide a laptop that can handle data conversion file volumes. | Infor CloudSuite | Rick Garcia | Oct 19 | Date needed | Open | Oct 19 · Ruth Spina |
Update log
Oct 20, 2026
Ruth Spina
Shipwell TMSShipwell SOW mapped to the program plan.
Shipwell stages and milestones added. BOL and pallet labels confirmed in Shipwell scope. Integration work assigned to the Dev and Data team. Dates proposed, to be baselined with the Infor plan on Nov 20.
Oct 19, 2026
Ruth Spina
Infor CloudSuitePre-kickoff executive alignment held.
Infor team introduced, T2V methodology reviewed, kickoff Oct 26, 2026, go-live June 1, 2027.
Oct 19, 2026
Jason Jennings
Infor CloudSuiteThree cloud environments provisioned.
TST, TRN and PRD confirmed; permissions, SSO and sample data still need follow-up.
Sep 23, 2026
Scott Lovett
Shipwell TMSShipwell SOW executed.
Go-live to be coordinated with Infor.